Case Background
This case arises from acquisition of land in village Gonawa, Naubatpur, Patna district, for construction of the Bihta–Sarmera State Highway No. 78.
The acquisition was started under the old Land Acquisition Act, 1894. Notifications were issued and the land was taken for the project. However, as on 1 January 2014, when the new Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act) came into force, no award had been declared under Section 11 of the 1894 Act.
Later, the award for this land was passed on 13 January 2015.
The landowners (appellants) filed a writ petition in 2014. They stated that no award had been made and therefore, under Section 24(1)(a) of the 2013 Act, compensation had to be calculated under the new law. They sought a direction that compensation be paid as per the 2013 Act.
The State filed a counter affidavit. On the date when the Single Judge decided the writ petition, 21 December 2016, the counter did not annex any copy of the award dated 13 January 2015.
Because of this, the Single Judge assumed that no award had yet been prepared under Section 11 of the 1894 Act. The writ petition was disposed of with directions to the District Land Acquisition Officer, Patna, to determine compensation by taking into consideration the provisions of the 2013 Act, on the assumption that no final award existed.
In compliance, the District Land Acquisition Officer and Additional District Land Acquisition Officer passed an order on 14 November 2017. This order relied on Government letters dated 4 December 2015 and 31 December 2015 and refused to apply full benefits of the 2013 Act to the appellants’ case.
The landowners then filed the present Letters Patent Appeal No. 136 of 2018 against the Single Judge’s judgment, also challenging the subsequent order dated 14 November 2017. There was a delay of 1 year and 7 days in filing the appeal. The Division Bench condoned this delay after finding sufficient cause.
What the Court Examined and Decided
The Division Bench of the Patna High Court, consisting of Hon’ble the Chief Justice and Hon’ble Justice Smt. Anjana Mishra, first noted the key undisputed facts.
It was common ground that:
(i) the 2013 Act came into force on 1 January 2014;
(ii) as on that date, no award under Section 11 of the 1894 Act had been made in this acquisition;
(iii) the award for the appellants’ land was eventually passed on 13 January 2015.
On these admitted facts, Section 24(1)(a) of the 2013 Act became central. The Court reproduced Section 24(1)(a): where no award under Section 11 of the 1894 Act has been made, all provisions of the 2013 Act relating to determination of compensation shall apply.
The Bench explained in simple terms that this provision starts with a strong “non obstante” clause. This means it overrides anything to the contrary elsewhere. If, on 1 January 2014, no award had been made under the 1894 Act, then for that acquisition the rules of the 2013 Act about how to calculate compensation must be used.
The 2013 Act itself, through Section 26, lays down how to determine market value of land. Once Section 24(1)(a) applies, the calculation of compensation has to follow Section 26 and other related provisions of the new Act, not the older method.
Against this clear statutory position, the Court then studied the Government’s letter dated 31 December 2015, issued by the Land Acquisition Directorate, Bihar.
The Hindi letter, when summarised, stated that in those cases under the old Land Acquisition Act, 1894, where award had not yet been pronounced, the market value date should be treated as 1 January 2014 for the purpose of compensation. However, it added an important qualification: it limited this benefit to cases where, up to 31 December 2015, no award had been declared or estimate approval granted at the level of the competent authority.
In other words, the State’s administrative instructions said that only if an award had not been pronouced up to 31 December 2015 would the 1 January 2014 rates be applied. Any award passed between 1 January 2014 and 31 December 2015, such as in this case on 13 January 2015, would be treated differently.
The District Land Acquisition Officer’s order dated 14 November 2017 simply followed this letter. It recorded that since the award in the appellants’ case had already been passed on 13 January 2015, i.e. before 31 December 2015, the Government letter prevented application of the 2013 Act rates as on 1 January 2014.
Instead, the authorities calculated compensation on the basis of rates prevailing at the time of notification under Section 4 of the 1894 Act. On that base rate, they doubled the amount, added 100% solatium, and added interest to arrive at the award figure.
The appellants argued that this approach was legally wrong. Their core submission was simple: once the law itself, in Section 24(1)(a), says that where no award existed as on 1 January 2014 the new Act applies, the State Government cannot by an executive instruction change this date. According to them, fixing a different cut-off date of 31 December 2015 had no basis in the statute and directly violated the 2013 Act.
On the other side, the learned Advocate General submitted that large issues regarding determination of compensation and lapsing of acquisition under the 2013 Act were pending before a Constitution Bench of the Supreme Court. He referred to several Supreme Court cases: Pune Municipal Corporation and another vs. Harakchand Misirimal Solanki and others, Yogesh Neema and others vs. State of Madhya Pradesh and others, and Sree Balaji Nagar Residential Association vs. State of Tamil Nadu, and the reference in Indore Development Authority vs. Shailendra (dead) through Lrs. & Ors.
He also argued that, since an award had already been delivered, the appellants had a statutory right of appeal against that award under the 2013 Act. Therefore, according to him, no further interference by the High Court was necessary. He further claimed that the rates of the new Act had been applied in the award, so there was no real grievance.
The Division Bench carefully considered these rival stands.
First, on the statutory position, the Bench was clear. The date of enforcement of the 2013 Act was 1 January 2014. Section 114 of the 2013 Act repealed the 1894 Act. Section 24(1)(a) made it mandatory that in every case where no award had been made under Section 11 of the 1894 Act before that date, the new Act’s provisions for determination of compensation must apply.
The Court emphasised that there was “no room for doubt” on this point. Therefore, for all awards made after 1 January 2014, including the award dated 13 January 2015 in this case, the applicable rates for compensation had to be those determined under the 2013 Act as on 1 January 2014.
Secondly, the Bench examined the Government letter of 31 December 2015. It held that the letter effectively extended or modified the applicability date fixed by the statute. By saying that the 1 January 2014 rates would apply only if the award had not been declared up to 31 December 2015, the Government had created an artificial second cut-off date.
The Court found this impermissible. An executive communication cannot override or amend a statute. The Bench remarked that this “artificial creation” of another cut-off date had “neither any logic nor any reason to support” and had no statutory force. Being contrary to the intention of the 2013 Act, it could not be used to calculate compensation.
Thirdly, the Court looked at the Single Judge’s earlier order. The Single Judge had assumed that no award existed and therefore directed the District Land Acquisition Officer to decide the matter on representation. In fact, the award had already been passed on 13 January 2015. The Bench observed that the Single Judge had proceeded “on an assumption of the non-existence of the Award which was not correct.”
Because of this mistaken assumption and the later reliance on the Government letter, the award was not framed according to the correct legal position under the 2013 Act. Sending the appellants back to file an appeal against the 2015 award would only prolong litigation that had started from this wrong legal foundation.
Taking note also of an earlier interim order of a Division Bench in connected Letters Patent Appeal No. 1615 of 2017 directing status quo, the Court decided to exercise its extraordinary jurisdiction to set things right comprehensively.
The Division Bench therefore:
(i) declared that the Government letter dated 31 December 2015, being contrary to the 2013 Act, could not be enforced in relation to any award made after 1 January 2014;
(ii) quashed the District Land Acquisition Officer’s order dated 14 November 2017 which had denied benefit of the 2013 Act rates based on that letter;
(iii) held that the award dated 13 January 2015 was not in compliance with the rates applicable as on 1 January 2014 and therefore had to be revised.
The Court directed the Collector to modify the award by applying the rates that would be applicable with effect from 1 January 2014 under Section 24(1)(a) read with Section 26 of the 2013 Act. The entire exercise of modification was to be completed within three months from the date of the judgment.
The Bench also made it clear that, while re-working the award, the authorities could not use the Government letter dated 31 December 2015 as the basis for any calculation.
Landowners were given the right to submit claims and objections about applicable rates before the Collector, who must consider and decide them strictly as per the 2013 Act.
Further, if on recalculation it was found that the appellants were entitled to more compensation, the Collector had to ensure prompt payment of the additional amount, along with all consequential benefits under the 2013 Act, within three months from the date of the modified award.
Finally, the Division Bench set aside the Single Judge’s judgment dated 21 December 2016 subject to the above modifications and disposed of the Letters Patent Appeal accordingly.
Why This Judgment Matters
This judgment is very important for landowners whose land was acquired around the time the 2013 Act came into force.
Many acquisitions in Bihar and elsewhere were started under the old 1894 Act but awards were passed after 1 January 2014. For such cases, this decision makes it clear that compensation has to be calculated strictly under the 2013 Act if no award existed on 1 January 2014.
The Patna High Court has firmly held that the State Government cannot, by circulars or letters, push forward or change the cut-off date given in the law. Any attempt to deny landowners benefits of the 2013 Act by creating new dates such as 31 December 2015 is unlawful.
Practically, this offers support to villagers and other land losers who feel that they were underpaid because officials followed State circulars instead of the statute. It also guides Collectors and Land Acquisition Officers that their calculations must be rooted in the clear wording of Section 24(1)(a) and Section 26, not in later administrative instructions.
Legal Issues and Answers
- Issue: Can the State Government fix a later cut-off date by executive instructions for applying compensation rates under the 2013 Act, when Section 24(1)(a) already governs cases where no award existed on 1 January 2014?
Answer: No. The Patna High Court held that the Government letter dated 31 December 2015, which limited the benefit of 1 January 2014 rates only to cases where no award existed up to 31 December 2015, was contrary to the 2013 Act and unenforceable. - Issue: How should compensation be determined for land acquisitions begun under the 1894 Act where the award was passed after 1 January 2014 but before 31 December 2015?
Answer: In such cases, since no award existed on 1 January 2014, all provisions of the 2013 Act relating to determination of compensation apply. Awards like the one dated 13 January 2015 must be revised to reflect rates as on 1 January 2014 under Section 26 of the 2013 Act. - Issue: What relief should be granted when an award is based on an incorrect understanding of the law due to an invalid executive instruction?
Answer: The Court directed the Collector to modify the award in line with the 2013 Act within a time-bound period, allow the landowners to raise objections on rates, and ensure prompt payment of any additional compensation with consequential benefits.
Cases Cited by the Court
- Pune Municipal Corporation and another vs. Harakchand Misirimal Solanki and others, (2014) 3 SCC 183
- Yogesh Neema and others vs. State of Madhya Pradesh and others, (2016) 6 SCC 387
- Sree Balaji Nagar Residential Association vs. State of Tamil Nadu, (2015) 3 SCC 353
- Indore Development Authority vs. Shailendra (dead) through Lrs. & Ors., (2018) SCC Online SC 100 (reference order noted)
Case Details
Case Number: Letters Patent Appeal No. 136 of 2018 in Civil Writ Jurisdiction Case No. 9089 of 2014
Case Title: Sihasan Prasad & Ors. vs. The State of Bihar & Ors.
Citation: 2019 (3) PLJR 519
Coram: Hon’ble the Chief Justice Amreshwar Pratap Sahi and Hon’ble Mrs. Justice Anjana Mishra
Advocates: Mr. Gopal Govind Mishra, Advocate for the appellants; Mr. Lalit Kishore, Advocate General for the State; Md. Khurshid Alam, AAG-12; Mr. Manish Dhari Singh, A.C. to A.G. for the respondents
Nature of the Case: Letters Patent Appeal (intra-court appeal) arising out of writ proceedings concerning land acquisition compensation and applicability of the 2013 Act
Link to Judgment: Patna High Court Judgment – LPA No. 136 of 2018
If you found this explanation helpful and wish to stay informed about how legal developments may affect your rights in Bihar, you may consider following Samvida Law Associates for more updates.


